Built on the Rock May Update

One of the Scripture readings assigned for Sunday May 7th (1 Peter 2:4-6) ties in especially well with the goals of our building project. Check out Pastor Enstad's video devotion here.



CONSTRUCTION PROGRESS

Our most recent construction video shows basement walls poured and the backfill process begun. Thanks to our member Nathan Hepner for capturing these drone videos.


CONSTRUCTION TIMELINE

God willing...

  • Back filling to be completed the week of 05/08

  • Grading north end parking lot. Week of 05/08

  • Pour Basement Floor – 05/11 & 12

  • Clay St. entrance paving – week of 05/15

  • Basement Masonry – week of 05/15

  • WPS hydro switch to permanent source – 05/26

  • 1st floor precast – 05/29

  • 1st floor masonry – 06/05

  • 2nd floor precast – 06/19

  • 2nd floor masonry – 06/26

  • Set bar joist – 07/17

  • Playground equipment fix – after school is out.

  • Completion Date 12/01/23


GIFTS AND PLEDGES

When we began our three-year Built on the Rock campaign our prayerful goal was $1 million in commitments and gifts. The chart below shows how the Lord has moved hearts to give above and beyond their regular offerings to St. Paul since that time. To God alone the glory!



COMMUNICATION

  • The best way to keep up with building project news is to visit our website blog and follow the link to subscribe.

  • To get a good overview of the whole project, including project history, visit our building project web page.

  • To view previous project videos, check out the Built on the Rock playlist on our YouTube channel.


GIFTS

  • To create or renew a financial commitment form for the project, click here.

  • To give a gift, click here.


Jesus said, "Therefore everyone who hears these words of mine and puts them into practice is like a wise man who built his house on the rock." Matthew 7:24





Recent Posts

See All
bottom of page